Construction Update – Dec 2, 2015

Sidewalk, Curbs and Gutters
Work on curbs and gutters has completed. A small section of sidewalk remains that is planned to be completed by Nov 11th, Insha Allah.

Asphalt Paving

Asphalt paving of the entire parking lot has been completed on Nov 25th, Alhamdu lillah. Striping (marking individual parking spaces) is in progress now. The Masjid is now accessible through all three entrances from Brushy Creek Road. As always, please exert caution while driving within the ICBC premises and make sure to park in designated spots only.

Electrical work and Parking lot lights
We are in the process of securing quotes for electrical work, including installation of parking lot lights. PEC (electric company) will be installing a new transformer at ICBC, we are awaiting the exact date of installation (from PEC). As part of the electrical plan, we will be installing concrete base for lighting as well as conduits for wiring.

Basket Ball Court
Concrete has been poured and we are now awaiting to resume the remaining work (acrylic coating, court markings, installing hoops and a secure fence around court, etc), which is expected to resume shortly, Insha Allah.

Landscape and Irrigation
We have finalized the contracts for the landscape and irrigation, Alhumdulillah. The irrigation work has already started and the landscape work is expected to follow in another week Insha Allah. This will be the final step in the Phase I construction.

Status of the current (existing) parking lot
As already announced earlier, this area will not be demolished during this phase. The temporary (ramp) access to this lot has been removed and this space can no longer be used for parking. Instead, we will use this space for community events and children’s play area, Insha Allah. This lot will be removed during the next phase (Masjid construction).