Construction Update – Jan 4, 2016

Sidewalk, Curbs and Gutters
Sidewalk, curbs and gutter work has completed, Alhumdulillah.

Parking Lot

Asphalt paving of the entire parking lot including striping has been completed, Alhamdu lillah. As always, please exert caution while driving within the ICBC premises and make sure to park in designated spots only. Signs around the property have been installed. Please follow all posted signs when driving inside ICBC.

Electrical work and Parking lot lights
PEC (electric company) will be installing a new transformer at ICBC, this month. We are yet to get an exact date (from PEC). Installing the conduits and wiring for the parking lot lights will commence this week, Insha Allah.

Basket Ball Court
Concrete has been poured and we are now awaiting to resume the remaining work (acrylic coating, court markings, installing hoops and a secure fence around court, etc).

Landscape and Irrigation
Irrigation work is about 80% complete and the landscape work is expected to follow in another week Insha Allah. This will be the final step in the Phase I construction.

Status of the current (existing) parking lot
As already announced earlier, this area will not be demolished during this phase. The temporary (ramp) access to this lot has been removed and this space can no longer be used for parking. Instead, we will use this space for community events and children’s play area, Insha Allah. This lot will be removed during the next phase (Masjid construction).