Masjid Construction Update-November 23, 2017

Alhamdu lillah, we are pleased to share the good news that we passed all the required inspections for pouring concrete for the slab.  These include (1) Structural engineering inspection (2) Foundation inspection by third party agency (per City Code), and (3) Plumbing, fire sprinkler and foundation inspections by the City.
Pouring of concrete is scheduled for Monday early morning, Insha Allah and will take about 12 hours to be completed.  This will be a major milestone for us, Alhamdu lillah.