Masjid Construction Update-September 1, 2017

The recent rains have delayed the construction work by 2-3 days.  Water and dirt from the drilled holes have been removed. 

A safety fence and silt fence have been installed around the work area. 

 

 

 

 

 

 

The process of fabricating steel columns has resumed.  The next step is to install the steel columns inside the drilled holes.

Pouring of concrete for piers is scheduled for next week, InShaAllah.  The steel frame for the foundation pad is expected to be ready in about two weeks, InShaAllah.