Masjid Construction Update-September 15, 2017

The process of fabricating steel columns has resumed after storm-related delays.  The framing of the foundation boundary is complete.  Trenching for plumbing is complete and plumbing piles will be in place by tomorrow.

City inspections for framing of boundary and plumbing will be done in the next few days.  The next step is to install electrical & other low voltage sleeves before installing steel columns inside the drilled holes with Anchor Bolts.  Rest of the foundation steel will be here for foundation pad.


Pouring of concrete for piers is scheduled for next week, InShaAllah, depending on City inspection.  The steel frame for the foundation pad is expected to be ready within one to two weeks, InShaAllah.