Masjid Construction Update-September 22, 2017

The framing of the foundation boundary and the plumbing work are complete and inspected by the City.  Termite treatment has been completed and inspected as well.  Electrical & other low voltage contractors visited the site and no sleeves were needed under the foundation.  Delivery of foundation steel has been delayed. Service contract with our structural engineer has been signed to [...]
Read More

Masjid Construction Update-September 15, 2017

The process of fabricating steel columns has resumed after storm-related delays.  The framing of the foundation boundary is complete.  Trenching for plumbing is complete and plumbing piles will be in place by tomorrow. City inspections for framing of boundary and plumbing will be done in the next few days.  The next step is to install electrical & other low voltage sleeves [...]
Read More

Masjid Construction Update-September 1, 2017

The recent rains have delayed the construction work by 2-3 days.  Water and dirt from the drilled holes have been removed.  A safety fence and silt fence have been installed around the work area. Pouring of concrete for piers is scheduled for next week, InShaAllah.  The steel frame for the foundation pad is expected to be ready in about two [...]
Read More