Masjid Construction Update-November 27, 2017

The pouring of concrete for the future masjid slab commenced on Monday early morning and was completed by mid-day, Alhamdu lillah.  This is indeed a major milestone for us! ICBC attendees cannot miss the new concrete slab as they approach the current masjid!
Read More

Masjid Construction Update-November 23, 2017

Alhamdu lillah, we are pleased to share the good news that we passed all the required inspections for pouring concrete for the slab.  These include (1) Structural engineering inspection (2) Foundation inspection by third party agency (per City Code), and (3) Plumbing, fire sprinkler and foundation inspections by the City. Pouring of concrete is scheduled for Monday early morning, Insha [...]
Read More

Masjid Construction Update-November 17, 2017

Excellent progress on the foundation work this week, Alhamdu lillah.  Due to the rain forecast on Thursday of this week, the pouring of concrete has been re-scheduled for next Tuesday, InShaAllah.  City inspections and engineering inspections have also been moved to this Friday and Sunday, respectively. We are taking the necessary steps to get ready for pouring concrete.

Read More

Masjid Construction Update-November 4, 2017

Great progress this week, Alhamdu lillah.  Trenching is complete.  Installation of vapor barrier sheet and 8" cardboard riser has started.  Iron rebars are being assembled for underground beams.  Next week, we will bind the foundation steel and get the necessary inspections completed, InShaAllah.  If everything goes as planned, pouring of concrete is scheduled for Saturday, November 11th, InShaAllah