Construction Update September 2020

Alhamdu lillah, our new masjid construction is progressing very well. Please see below update.

Sheetrock work is fully complete except at the dome.
Ceiling grid installation has been completed.
Ceiling speakers have been installed.
Electrical work is in progress. Lights are being installed.
Testing of lights underway
Chandelier installation is in progress.
Bathroom tile work and wudu area is in progress.
Calligraphy work is in progress. Expect to complete in 2-3 weeks.
Shoe racks are being built.
Interior door installation ongoing.
Side walkways is 90% complete.
Flooring work is in progress.

Checkout some of the interior pictures here

Scroll down to the end!

We are in the stage of high cost finishing work and humbly request community members to fulfill their donations pledges as soon as possible.