As tragedy continues to strike around the world, we must stay vigilant. As we all know, 50 of our Brothers and Sisters were killed during Ju’maah prayer in New Zealand. While we take the necessary steps to protect ourselves, our loved ones, and our community, it is important to remember that We Are Not Alone.

Read More

Construction Update Oct 19th

Rain this week has hampered the construction activity; yet good progress made in the staircase work this week. Framing started today, Alhamdu lillah. All air-conditioning units have been installed on the roof top and hangers are in place to support the ducts. Ducting material is onsite now and A/C duct work will start soon, InShaAllah.
Read More

Construction Update Sep 27th

Steel binding inspection completed and concrete has been poured for the 2nd floor, Alhumdu lillah.
Following are the tasks for the next few weeks: Build the staircases to the 2nd floor; Framing.